The new Act will impose much greater liabilty on developers to obtain detailed design approval to surface water drainage at the Planning Stage rather than at detailed design stage. JNP Group have extensive experience of cost effective approaches to surface water drainage strategy and design and will be pleased to help you....

Read More


consulting engineering, structural engineering, traffic engineering, flood risk prevention, civil engineering, rail engineering

As part of a large residential development on a brownfield former gas works a new bridge was required, where a new section 38 road was required to span a new artificial stream, designed and detailed by JNP Group.

The stream resulted from the opening up of an existing culverted water course across the site.

Negotiations with the Environment Agency and Inland Drainage Board dictated the span and stream profile.

consulting engineering, structural engineering, traffic engineering, flood risk prevention, civil engineering, rail engineering

consulting engineering, structural engineering, traffic engineering, flood risk prevention, civil engineering, rail engineering

Approvals were also required from Kent County Council, the adopting authority. An Approval In Principle (AIP) was submitted proposing the use of a precast concrete culvert, with brick clad reinforced insitu parapets and wing walls. Alternative designs considered included sheet piled or reinforced concrete abutments with an insitu or precast concrete deck. A form C in accordance with HD22 was provided as part of the AIP submission.

The carriageway profile was amended to allow for future maintenance and departures from standards (relaxation of barrier requirements) were agreed with KCC as part of the approvals process.

Following completion and signing of the AIP detailed design and drawings were completed and drawings, specification, including testing regime and design certificates were submitted to KCC. This included drawings and design certificates from the precast concrete supplier. All designs were in accordance with the Highway Agency BD documents and BS5400, as listed in the Technical Approved Schedule (TAS) section of the AIP.

consulting engineering, structural engineering, traffic engineering, flood risk prevention, civil engineering, rail engineering

Whilst technically a category 1 structure in accordance with BD02/05 KCC required the structure to be classed as category 3 structure and undertook the design check.

JNP Group undertook regular site inspections during the construction period.

consulting engineering, structural engineering, traffic engineering, flood risk prevention, civil engineering, rail engineering

consulting engineering, structural engineering, traffic engineering, flood risk prevention, civil engineering, rail engineering

JNP Brochure
Latest Case Study
JNP Office Locations

Our Brochure

Download our company brochure as a PDF.

Latest Case Studies

View detailed information about all our latest projects.

Office Locations

Get in touch – Details of our UK Offices and Key Personnel.