The new Act will impose much greater liabilty on developers to obtain detailed design approval to surface water drainage at the Planning Stage rather than at detailed design stage. JNP Group have extensive experience of cost effective approaches to surface water drainage strategy and design and will be pleased to help you....
JNP Group consulting engineers services provided:
The quarry is some 39 metres deep of which 60% has been backfilled with end tipped Thanet sand and the remaining 40% partially backfilled with Whiting Dross (surplus slurry from the production of White Portland Cement). This material the past has been has been used as filler for comment medicines, toothpaste and as an additive in the manufacture of bricks to form imperfections and give the illusion of a hand made brick.
Redevelopment of this 20 acre into a residential development faced some daunting geotechnical and environmental considerations. These were as follows:-
JNP Group consulting engineers carried out extensive Geo-environmental investigations and following lengthy consultations with Kent County Council and the NHBC as Building Regulation Authority, gained approval to the following methodology.
Our Brochure
Download our company brochure as a PDF.
Latest Case Studies
View detailed information about all our latest projects.
Office Locations
Get in touch – Details of our UK Offices and Key Personnel.